Trident Power JB
Trident Power JB is establishing a small run-of-canal power project in the Province of Punjab, Pakistan. The power generated shall be supplied to a 8 Ton steel furnace for the production of billets for further sales to the market in Pakistan. The powerhouse and the associated steel industry shall be owned by Trident Power Limited.
Location | Okara Punjab – Pakistan |
Overall Power Generation Capacity to be generated | 4.6 MW |
Available Water Head after Construction Works of Plant | 3.1 meters |
Total Water Discharge Design/rated | 56.64 m3/s |
Type of Turbines to be Installed with available water head | Kaplan Turbines |
No. of Turbines Required | 03 Nos |
Rated Output Capacity of each Turbine | 1.533MW |
Project tentative timeline | ~24 months |
Commercial Operation | February 2025 |
Trident Power GR
A detailed overview of the Lower Chenab Canal Hydropower Project, including its location, capacity, and expected timeline for completion. You can include images, maps, and diagrams to help explain the project.
Location: | Wazirabad Punjab – Pakistan |
Overall Power Generation Capacity to be generated: | 7.55 MW |
Available Water Head after Construction Works of Plant: | 3.5 meters |
Total Water Discharge Design/rated: | 250 m3/s |
Type of Turbines to be Installed with available water head: | Kaplan Turbines |
No. of Turbines Required: | 04 Nos |
Rated Output Capacity of each Turbine: | 1.95 MW |
Project tentative timeline: | ~27 months |
Commercial Operation: | June 2025 |